Work at Facility 00UGR (Sludge Dump) as part of the construction of the Rooppur NPP in Bangladesh

At the end of February, RoinWorld began work at Facility 00UGR (a sludge dump with a clarified water pumping station) as part of the construction of the Rooppur NPP in the People’s Republic of Bangladesh.


Official video – Rooppur NPP, Bangladesh

In this video, we summarize our first results and talk about the achievements of RoinWorld in the construction of the Rooppur NPP from 2017 to 2019


Vertical layout arrangement – site 9 of the Rooppur NPP

On November 20, RoinWorld completed work on Site No. 9 (vertical layout) as part of the Rooppur NPP construction. The total volume of washed sand was 173.570 m3.


Vertical layout arrangement – site 10 of the Rooppur NPP

At the end of September 2019, RoinWorld completed work on Site 10 (vertical layout) as part of the construction of the Rooppur NPP.


RoinWorld construction works at the SMB-2 of the Rooppur NPP in Bangladesh

As a reminder, work has been underway since February 2018. For this moment, 26 sites out of 41 have been commissioned.


Metal structures, 37 sites, Rooppur NPP

RoinWorld is performing installation of metal frame structures, wall and roof panels at 37 sites of the SMB-2 as part of the construction of the Rooppur NPP (Bangladesh).


RoinWorld completed work on site 4.1, Rooppur NPP

One of the 41 sites to be commissioned by RoinWorld, the production building of the pre-assembly workshop with a total area of 4300 m2 is equipped with five overhead cranes and lifting mechanisms.


Vertical layout arrangement – site 11 of the Rooppur NPP

On July 27, 2019, RoinWorld completed work on site 11 (vertical layout) in the framework of the Rooppur NPP construction


Roinworld, together with AtomStroyExport, conducted firefighting training exercises at the Rooppur NPP.

Roinworld, together with AtomStroyExport, conducted firefighting training exercises at the Rooppur NPP.


Vertical layout arrangement – site 19 of the Rooppur NPP

On March 18, 2019, RoinWorld completed work on site 19, the total volume of washed sand was 902,000 m3.


Vertical layout arrangement – site 18

On November 30, 2018, RoinWorld completed work on site 18.
As a reminder, site 18 is part of the vertical planning project, work on which has been carried out by RW specialists since spring.


Completion of work at the Training Center site

In early December, RoinWorld completed work on the Training Center site (underground part of the building), namely the installation of monolithic structures: foundations, walls, columns and floors below the 0.000 mark.


Production of works on the site of the Training Centre

In the end of June, RoinWorld started works on the Training Centre facilities, particularly the installation of monolithic structures in the foundation pit, walls, columns, and floors below the level 0.000


The device of vertical planning – 19 plot

On the 1st of April, Roin World began preparatory work for the vertical layout of site 19.