As a reminder, work has now been completed on sites 18, 19, 11, and 10.

Site 18 – 264.000 m3 (16 maps)
Site 19 – 902.000 m3 (39 maps)
Site 11 – 677. 000m3 (42 maps)
Site 10 – 503.000 m3 (54 maps)

RoinWorld specialists have yet to complete work on 7 more sites of the vertical layout: 8, 9, 13, 14, 15, 16, and 17.

It should be noted that the RoinWorld company’s own laboratory takes an active part in performing work on each site, and in tandem with Construction Supervisors it carries out control over the layout and compaction of the soil.