At the end of September 2019, RoinWorld completed work on Site 10 (vertical layout) as part of the construction of the Rooppur NPP. The sand was washed using 2 dredgers along 3 lines of the slurry pipeline on 54 maps with an average of 12 layers (minimum – 7, maximum – 14, depending on the terrain).

The total volume of washed sand was 503.366 m3.

It should be noted that more than 50 units of construction equipment were involved in work: excavators, bulldozers, soil compactors, dump trucks and loaders.
From the very beginning, the RoinWorld’s own laboratory took an active part in work, and in tandem with Construction Supervisors it carried out control over the layout and compaction of the soil.